Netrality Properties
Philadelphia, PA
Expertise
Mechanical
Electrical
Plumbing
Fire Protection
Structural
Technology Infrastructure
Security
Project Type
Size
1,300,000 SF
This project started with a Facility Conditions Assessment, followed by a Feasibility Study, and then a Capital Budget Development. Bala provided MEP/FP, structural and technology engineering services for the infrastructure replacement for this 1,300,000 SF, 1920’s era building, upgrading it to a 56 MW facility. Bala designed new MEP/FP and technology riser shafts, and infrastructure replacements for switchgear, substations, risers, cooling towers, piping, and generators for the building. All upgrades were implemented in the live facility and all mission critical systems remained operational.